Nissan Rogue (T33) 2021-Present Service Manual: P1c95-13 Ignition Power Supply Circuit

DTC Description

DTC DETECTION LOGIC

DTC No. CONSULT screen terms (Trouble diagnosis content) DTC detection condition
P1C95-13

Ignition power supply circuit

(Ignition power supply circuit)
Diagnosis condition Engine running at idle
Signal (terminal) Ignition power supply
Threshold 1.5 V or less
Diagnosis delay time 5 second or less

POSSIBLE CAUSE

  • Sub starter & generator

  • Harness or connectors (Ignition power supply circuit is open or shorted.)

  • IPDM E/R

FAIL-SAFE

When the sub starter & generator rotation rises, starts even if the ignition power not supply.

DTC CONFIRMATION PROCEDURE

PERFORM DTC CONFIRMATION PROCEDURE

CONSULT

  1. Start the engine and let it idle and wait for 2 seconds or more.

  2. Select “Self diagnosis result” mode of “Sub starter & generator”.

Is DTC detected?

YES>>

Refer to Diagnosis Procedure.

NO-1>>

To check malfunction symptom before repair: Refer to Intermittent Incident.

NO-2>>

Confirmation after repair: Inspection End.

Diagnosis Procedure

CHECK FUSE

  1. Ignition switch OFF.

  2. Check that the following fuse is not blown (open):

    Location Fusible No. Capacity
    IPDM E/R 71 10 A

Is the fuse blown (open)?

YES>>

Replace the blown (open) fuse after repairing the affected circuit if a fuse is blown (open).

NO>>

GO TO 2.

CHECK IGNITION OUTPUT VOLTAGE

  1. Disconnect sub starter & generator connector.

  2. Ignition switch ON.

  3. Check voltage between sub starter & generator harness connector and ground.

    (+) (-)

    Voltage

    (Approx.)
    Sub starter & generator
    Connector Terminal
    F126 4 Ground Battery voltage

Is the inspection result normal?

YES>>

Replace sub starter & generator. Refer to Removal and Installation.

NO>>

GO TO 3.

CHECK IGNITION OUTPUT VOLTAGE CIRCUIT

  1. Ignition switch OFF.

  2. Disconnect IPDM E/R connector.

  3. Check continuity between IPDM E/R harness connector and sub starter & generator harness connector.

    Sub starter & generator IPDM E/R Continuity
    Connector Terminal Connector Terminal
    F126 4 F35 71 Yes
  4. Check continuity between sub starter & generator harness connector and ground.

    Sub starter & generator - Continuity
    Connector Terminal
    F126 4 Ground No

Is the inspection result normal?

YES>>

Replace IPDM E/R. Refer to Removal and Installation.

NO>>

Repair or replace harness.

    P1c92-82 Communication Error
    DTC Description DTC DETECTION LOGIC DTC No. CONSULT screen terms (Trouble diagnosis content) DTC detection condition P1C92-82 Communication error (Communication error) Diagnosis...
    U007a-00 Control Module Comm Bus H Off
    DTC Description DESCRIPTIONCAN (Controller Area Network) is a serial communication line for real time applications. It is an on-Nissan Ariya vehicle multiplex communication line...

    Other materials:

    Action Test
    Ldw Work Procedure Perform action test to verify the customer's concern. Perform action test and check the system operation after system diagnosis. WARNING: Be careful of traffic conditions and safety around the vehicle when performing road test. CAUTION: Fully understand the ...

    Additional Service When Replacing Abs Actuator and Electric Unit (control Unit)
    Work Procedure DescriptionWhen replacing the ABS actuator and electric unit (control unit), the procedures of BEFORE REPLACEMENT and AFTER REPLACEMENT must be performed.BEFORE REPLACEMENTWhen replacing the ABS actuator and electric unit (control unit), save “Operation log”.AFTER REPLACEMENT ...

    Basic information
    WARNING Always confirm the liftgate of the Nissan Rogue is securely closed before driving. Never drive with the liftgate open to prevent exhaust gases from entering the cabin. Do not leave children, pets, or dependent persons inside the Nissan Rogue unattended. Keep hands and feet clear of the ...